Cremation systems Display Commissioning

You want to run a crematorium? Then you must report the system to the responsible immission control authority before commissioning.

As the operator of a cremation facility, you must notify the competent authority of this at least one month before commissioning. The competent authority shall examine the notification and record the installation in its plant register.

  • written notification

Related Links

  • ยง 6 Ordinance on Cremation Facilities (27th BImSchV)

The notification shall be submitted in writing by post or electronically to the competent authority.