Display installation and decommissioning of publicly accessible charging points Unfortunately this specification of service has not yet been completely translated.

If you put publicly accessible normal and fast charging points into or out of operation, you must notify the Federal Network Agency. You must also notify the Federal Network Agency if you make private charging points public or transfer your charging points to another operator.

You must notify the Federal Network Agency (BNetzA) of charging points when you

  • set up or decommission publicly accessible normal and fast charging points for electric vehicles with a charging capacity of more than 3.7 kilowatts.
  • make private charging points public or transfer your publicly accessible charging points to another operator.

The obligation to notify applies to all normal charging points that were put into operation after 17.03.2016 and to all fast charging points.

  • Standard charging points have a maximum charging capacity of 22 kilowatts.
  • Rapid charging points have a charging capacity of more than 22 kilowatts.
  • A charging point is publicly accessible if it is located either in the public street space or on private property and the parking space belonging to the charging point can be used by any person.



Operators of fast charging points must additionally prove compliance with the technical requirements of the ordinance by enclosing a commissioning report signed by a qualified electrician.

  • Forms: yes
  • Online procedure possible: yes
  • Written form required: no
  • Personal appearance required: no

Related Links

  • Online-Formular Ladepunktanzeige
  • Vorlage für ein Inbetriebnahmeprotokoll für Ladeeinrichtungen im Sinne der Ladesäulenverordnung (LSV)
  • Vorlage für die Meldung eines Betreiberwechsels
Bundesnetzagentur Referat 620 Ladepunktanzeige

Preconditions

You are planning to install a publicly accessible charging point or already operate publicly accessible normal or fast charging points.

Related Links

  • § 5 Absätze 1 und 4 Ladesäulenverordnung

Related Links

  • Leitfäden und Merkblätter zum Thema Ladepunkte auf der Internetseite der Bundesnetzagentur
  • Oft gestellte Fragen zum Thema Ladepunkte auf der Internetseite der Bundesnetzagentur

You can place the advertisement via online form.

Notification of installation or decommissioning via an online form:

  • Go to the Federal Network Agency's website and open the online form.
  • Complete the online form and upload the required documents.
    • You can also submit the additional documents by e-mail or by post.
  • Submit the form electronically.
  • The Federal Network Agency will check your notification.
  • You will receive written information by e-mail with your data entry and, if applicable, an operator number.
  • The Federal Network Agency will publish the charging points on its website if the notification is complete and you have agreed to the publication.

Notification of a change of operator:

  • On the website of the Federal Network Agency you will find a "Form: Change of operator".
  • Complete the form in full and send it by e-mail to the mailbox for the charging point ordinance of the Federal Network Agency.
  • The Federal Network Agency will confirm receipt and processing of the information by e-mail.

Responsible for the content
No information available

Last update or date of publication
07.09.2021