Operation of an energy supply network Approval

If you intend to operate an energy supply network, you will need approval from the competent authority under national law.

information on the network (acquisition, establishment of a new network, investment, network capacity, presentation of the network), information on the customers whose supply is to be taken up; information on the gas/electricity supply of customers, Proof of the legal form of the company (commercial register extract, partnership agreement), Personnel and technical performance documents (organization chart with number of employees and their qualification), technical equipment (see VDN Directive S-1000 or DVGW Worksheet G 1000), presentation of contracts with subcontractors, Presentation of an income forecast statement (investments and depreciation, capital and financial plan, operating expenses, profit and loss account), Economic performance documents (proof of equity, shareholdings in the company, final profit and loss account).


A common indication of the application for authorisation to start operating an electricity/gas supply network in accordance with Section 4 of the Energy Economics Act (EnWG). See: https://mwe.brandenburg.de/de/energieaufsicht/bb1.c.478789.de . The application may also be processed through a single body, Section 4(5) of the EnWG.

Preconditions
You own the human, technical and economic performance and reliability to ensure long-term network operation in accordance with the statutory provisions.
Section 4 Energy Economics Act (EnWG)

The application must be addressed in writing to the Ministry of Economic Affairs and Energy of the State of Brandenburg.

Responsible for the content
Ministry of Economy and Energy

Last update or date of publication