Building permit granted for camping, weekend or golf courses

Information on building permits for campsites, weekend campsites and golf courses

If you want to build, expand or change the use of a camping, weekend or golf course, you need a permit.

With the building templates ( cf. § 3 Brandenburg Building Templates Ordinance ) a fire protection concept must be submitted for campsites and weekend house pitches.

In the fire protection concept, an overall assessment must be carried out on the basis of a risk analysis and presented which preventive structural, technical, organizational (operational) and defensive measures are necessary to meet the protection objectives of fire protection and the fire protection requirements.

Application forms

Preconditions

Please submit the building application in triplicate in paper form and additionally as an electronic copy. If the lower building supervisory authority has opened electronic access, it must be used. For your building application, you must use the prescribed forms.

If the construction of buildings is planned, the preparation of the building templates and a signature by a person authorized to submit a building template (design author) is required.

§ 72 Brandenburg Building Code

Brandenburg Camping and Weekend House Ordinance

In the building permit procedure, the project is fully examined. The lower building supervisory authority checks within two weeks of receipt of the application whether the building templates are complete and confirms receipt.

If the building templates are incomplete or defective, the client will be informed of a deadline for supplementing the building application with the confirmation of receipt.

The application is deemed to be withdrawn if the missing documents are not submitted in due time (§ 69 paragraph 2 BbgBO).

If the building templates are complete, the lower building supervisory authority immediately involves all specialist authorities whose interests are affected by the project, as well as the municipality. The deadline for the specialist authorities to comment is one month, the municipality has two months to grant the municipal agreement.

If all opinions have been submitted and there are no contradictions to public law regulations, the building permit must be issued. The building permit includes all necessary permits.