The simplified procedure is used for all construction projects that:
- are not special buildings
- do not require planning permission and
- are not subject to an exemption from approval.
In the case of building projects that are subject to the exemption from approval, the municipality can declare that a simplified building permit procedure is to be carried out. The client can request that the simplified building permit procedure be carried out.
In contrast to the full procedure, the scope of the building supervisory authority's review is significantly reduced in the simplified building permit procedure.
The subject of the examination is
- the compatibility of the project with building planning law
- Deviations, exceptions or exemptions applied for in accordance with § 73 HBO
- other regulations under public law insofar as the building permit eliminates or replaces a decision under these regulations
The building owner is responsible for ensuring that public law regulations that are not examined in the simplified building permit procedure are also complied with. In individual cases, a deviation, exception or exemption from public law regulations that do not need to be checked must also be applied for. In the event of a breach of these regulations, the building permit authority can stop the construction or have what has already been built demolished.
The building permit expires if you do not start construction work within 3 years of the permit being granted or if construction work has been interrupted for one year after this period. The period can be extended by up to 2 years in each case, even several times, with a written application.