As a rule, you require a building permit for the construction, erection, installation, modification, change of use, demolition and removal of (structural) installations or parts thereof.
For special buildings (e.g. high-rise buildings), planning permission is granted in the conventional planning permission procedure.
For other construction projects requiring approval, planning permission is granted in the simplified planning permission procedure.
You can apply for a building permit by submitting a building application together with the necessary documents digitally in the building portal or in analog form.
You may only start building once you have received the building permit.
The construction site sign must be visible from the public road.
The building permit expires if you do not start construction work within 3 years of the permit being issued or if construction work has been interrupted for one year after this period. The period can be extended by up to 2 years in each case with a written application.